Project: Kostolac B3 Phase II Section II – Procurement of the VI BTO System for the Drmno warranty period is currently ongoing.
Basic information on the procurement contract:
Contractual agreement for the construction of a new unit at Kostolac B3 with an output of 350 MW, between the Public Enterprise EPS and CMEC.
Public contracting authority:
Open Pit Mine
Project status (completed or ongoing):
Completed on 02.12.2019 (warranty period ended on 02.12.2021). The equipment is in regular operation.
Basic information on the procurement contract:
The contract provided for the delivery of equipment for a new VI BTO system aimed at increasing the capacity of the Drmno open-pit mine. The following mining machinery and equipment were procured:
- 1 (one) bucket-wheel excavator with a theoretical capacity of 6,600 m³/h
- 4 (four) drive stations with a belt conveyor system 5 km in length (belt width B = 2000 mm)
- 1 (one) spreader with a theoretical capacity of 8,500 m³/h
- Transformer station Rudnik 5 for electricity supply, 110/6 kV
Public contracting authority:
Elektroprivreda Srbije (EPS), Belgrade
Main contractor:
China Machinery Engineering Corporation (CMEC)
Procurement procedure:
Direct contracting based on an intergovernmental agreement
Availability of project information on the Ministry's website:
Information Guide of the Ministry of Mining and Energy:
https://www.mre.gov.rs/tekst/100/informator-o-radu.php
Project Package: Kostolac B – Section 1 – TPP Kostolac B3 (Phase II)
Project status (completed or ongoing):
Completed; the
Public Enterprise Elektroprivreda Srbije (EPS), Belgrade
Main contractor:
China Machinery Engineering Corporation (CMEC), P.R. China
Procurement procedure:
Direct contracting based on an intergovernmental agreement
Availability of project information on the Ministry’s website:
- https://www.mre.gov.rs/vest/6804/djedovic-handanovic-sa-predsednikom-kineskog-cmec-a-o-pustanju-u-rad-te-kostolac-b3.php
- Information Guide of the Ministry of Mining and Energy: https://www.mre.gov.rs/tekst/100/informator-o-radu.php
Construction of the Flue Gas Desulfurization Plant at TPP Nikola Tesla A3–A6
Project status (completed or ongoing):
Completed; the warranty period is currently ongoing.
Basic information on the procurement contract:
Contract signed with the contractor (Consortium: Mitsubishi Hitachi Power Systems Japan / ITOCHU Corporation Japan / Mitsubishi Hitachi Power Systems Europe GmbH Germany / MPP Jedinstvo AD Sevojno Serbia)
Contracting authority:
Public Enterprise Elektroprivreda Srbije (EPS), Belgrade
Main contractor:
Mitsubishi Hitachi Power Systems, Japan
Procurement procedure:
Direct contracting based on an intergovernmental agreement
Availability of project information on the Ministry’s website:
https://www.mre.gov.rs/vest/sr/2717/djedovic-handanovic-do-aprila-pustanje-u-probni-rad-postrojenja-za-odsumporavanje-u-tent-a.php
Automation of the Medium-Voltage Distribution Network
Project status (completed or ongoing):
Ongoing
Basic information on the procurement contract:
The procedure was conducted and the contract signed in accordance with the agreement between the Governments of the Republic of Serbia and the French Republic.
Public contracting authority:
Elektrodistribucija Srbije
Main contractor:
Schneider Electric France, Schneider Electric Serbia, Schneider Electric Novi Sad
Procurement procedure:
Public procurement procedures for the selection of contractors for the installation of the specified equipment will be conducted in accordance with the Public Procurement Law of the Republic of Serbia.
Availability of project information on the Ministry’s website:
- http://mre.gov.rs/vest/sr/418/djedovic-sa-francuskim-poslovnim-udruzenjem-medef-.php
- http://mre.gov.rs/vest/sr/1983/velike-mogucnosti-za-unapredjenje-energetske-saradnje-srbije-i-francuske.php
- http://mre.gov.rs/vest/sr/2274/djedovic-handanovic-i-ambasador-kosar-o-saradnji-francuskih-i-srpskih-kompanija-u-oblasti-energetike.php
- Information Guide of the Ministry of Mining and Energy: https://www.mre.gov.rs/tekst/100/informator-o-radu.php
Project: Construction of the Heating Pipeline Obrenovac – Novi Beograd
Project status (completed or ongoing):
Ongoing
Basic information on the procurement contract:
The contract was concluded between the City of Belgrade, Power Construction Corporation of China, and Public Utility Company Beogradske Elektrane on January 9, 2020. An annex to the main contract was signed on 11 October 2023.
Public contracting authority:
City of Belgrade / Public Utility Company Beogradske Elektrane
Main contractor:
Power Construction Corporation of China
Procurement procedure:
Direct contracting based on an intergovernmental agreement
Availability of project information on the Ministry’s website:
https://www.mre.gov.rs/tekst/100/informator-o-radu.php
Revitalisation of existing thermal power plant units Kostolac B1 and B2, part of state-owned energy giant EPS
Project status (completed or ongoing):
Completed
Basic information on the procurement contract:
Contractual agreement on the Revitalization of Blocks B1 and B2 at TPP Kostolac between PE EPS and CMEC
Public contracting authority:
Elektroprivreda Srbije (EPS), Belgrade
Main contractor:
China Machinery Engineering Corporation (CMEC)
Procurement procedure:
Direct contracting based on an intergovernmental agreement
Availability of project information on the Ministry’s website: https://www.mre.gov.rs/tekst/100/informator-o-radu.php